Internal Roads in Al Qusais Industrial Area 1,2,3,4 & 5

Project Location:
Al Qusais Industrial Area 1,2,3,4,5 - منطقة القصيص الصناعية 1, 2, 3, 4 , 5
Project End Date:
10-Oct-23
Project Description
- Extensive improvements on the internal roads and lighting
- Constructing 32 roads covering 10 kilometers
- Installing streetlights along 43,000 meters
Project Benefits
- Road capacity increased by 200%, from 500 vehicles per hour in both directions, to 1,500 vehicles per hour in both directions
- Improves access and exit points to over 320 workshops, 25 residential buildings, shops, and educational facilities
- Benefits an estimated 60,000 residents in the area